Monday 5 March 2012

Trenching begins

Stu finally started the trenching on Friday, and was working on it again over the weekend. He got about half way, then had great difficulties getting any grip with the kanga on the muddy fill. We've since realised that there may be a problem with where we will put the septic drains too, so he has now decided to fill in the trenching he has done, and start again with it on the other side of the driveway. Hopefully progress for this will be much quicker so we can get the electrician out then get on to the service connection so it can be ready and waiting once the transformer is installed.

The beginning of the trenching
He also worked on the shed on Sunday. All the top hat bracing is in place now, and he put a sheet up on one of the ends. Slow work when you are on your own in bad weather.


No comments:

Post a Comment